Satori Nusa Dua
Site report · August 2026From the August 2026 report: the first-floor slab of the apartment block is concreted and column reinforcement is under way; four villa pools are complete and roofing is progressing across the villa quarter; the groundwater tank and the electrical switchboard room are finished, with waterproofing of the underground structures in progress. Villa permit (PBG) in hand; managed on delivery by Accor.